Ituango Dam

Ituango Dam
Construction site in 2014
Ituango Dam is located in Colombia
Ituango Dam
Ituango Dam
Location of Ituango Dam in Colombia
Official namePescadero-Ituango "José Tejada Sáenz"
CountryColombia
LocationItuango
Coordinates7°07′50.04″N 75°39′48.7″W / 7.1305667°N 75.663528°W / 7.1305667; -75.663528
StatusUnder construction
Construction began2011
Opening date2022 (2 turbines)[1])
Construction costUS$3.8 billion
Dam and spillways
Type of dam
ImpoundsCauca River
Height225 m (738 ft)
Dam volume19,000,000 m3 (670,000,000 cu ft)
Spillway typeService, gate controlled
Spillway capacity22,600 m3/s (800,000 cu ft/s)
Reservoir
Total capacity2,720,000,000 m3 (2,210,000 acre⋅ft)
Active capacity980,000,000 m3 (790,000 acre⋅ft)
Surface area38 km2 (15 sq mi)
Maximum length127 km (79 mi)
Power Station
OperatorEPM Ituango
Hydraulic head197 m (646 ft) (nominal)
Turbines8 x 307 MW (412,000 hp) Francis type
Installed capacity2,456 MW (3,294,000 hp) (planned)
Annual generation9,200 GWh (33,000 TJ) (firm)
Website
hidroituango.com.co/es

The Ituango Dam, also referred to as the Pescadero-Ituango Dam or Hidroituango, is an embankment dam under construction on the Cauca River near Ituango in Antioquia Department, Colombia. The primary purpose of the project is hydroelectric power generation, and its power plant will have an installed capacity of 2,456 megawatts (3,294,000 hp) if completed. Preliminary construction on the dam began in September 2011, and the plant was expected to begin operations in late 2018. Heavy rainfall and landslides in April–May 2018 blocked the river's diversion tunnel, threatening a breach of the dam.[2] If completed, Ituango will be the largest power station in Colombia.[3]

Background

The development of the Ituango Dam project was proposed by EPM Ituango, a consortium of Empresas Públicas de Medellín (EPM) and the Antioquia government.[4] The dam's feasibility study was completed in 1983, but the project was shelved in the 1990s due to an economic crisis.[5] The final designs for the project were finished in 2008, and on 8 July 2011, the project management contract was awarded. Preliminary construction (surveying, roads, bridges, diversion tunnels) began in September 2011, with the expected completion date forecasted for 2013.[6] Main works started thereafter, and the power plant was expected to be commissioned in 2018. The total cost is expected to be US$2.8 billion.[7]

Design

The dam is planned to be a 225-metre-tall (738 ft) earth-fill embankment type with a clay core, with a volume of 19 million cubic metres (670×10^6 cu ft). Its reservoir will have a capacity of 2,720 million cubic metres (2,210,000 acre⋅ft), of which 980 million cubic metres (790,000 acre⋅ft) will be active (or "useful") capacity. The reservoir will be 127 kilometres (79 mi) long and cover an area of 38 square kilometres (15 sq mi). To maintain reservoir levels, the dam will have a spillway controlled by four radial gates with a design flow of 22,600 cubic metres per second (800,000 cu ft/s). The dam's power plant will have a nominal hydraulic head of 197 metres (646 ft) and contain eight 307-megawatt (412,000 hp) Francis turbine-generators.[8]

Diversion tunnel blockage

Three tunnels were constructed to divert the Cauca River around the construction site. Two were eventually sealed during construction, leaving a third to divert the river.[9] Between 28 April and 7 May 2018, three landslides blocked the tunnel, leading the reservoir to fill.[10] Engineers attempted to open the two closed tunnels with explosives but were unsuccessful.[9] On 10 May, when the reservoir reached the power-station intake, engineers began releasing water through the unfinished powerhouse to prevent a breach of the dam.[11] On 12 May, one of the previously sealed tunnels naturally reopened, which suddenly increased downstream flows by three times the average.[12] This prompted evacuations downstream, eventually totaling around 25,000 people.[13]

On 16 May, silt buildup in a portion of the powerhouse, the only means to drain the reservoir, led to water escaping into a transit gallery used by construction vehicles. The water eventually poured onto the downstream face of the dam, eroding the roadway and a portion of the riprap.[14] Subsequently, EPM announced that a risk of collapse existed, and workers continued to fill the dam to its design height in hopes that the spillway could be used to prevent an over-topping of the dam.[15] Heavy rainfall was expected in the Cauca River basin through the end of May.[16]

On 19 May, the dam works reached an elevation of 405 m, 5 m below the cofferdam's target level.[17] On 25 May, the Colombian Society of Engineers issued a letter expressing their panic about the situation, stating that the "Ituango project is dead and there is no control over it, so the most natural thing is to expect it to fail; we are sure that it is easier to fail than not to fail, and we are truly in a panic".[18]

Environmental impact

Some sources have argued that the dam construction has severe ecological consequences, and displaced families, environmentalists, youth groups, and concerned locals have opposed the project.[19] Other publications have argued that the project will benefit millions through extra revenue towards social and infrastructure programs.[20]

In February 2019, the project came under increased pressure from local and national governmental regulatory agencies[21] because of the closure of the river flow and the downstream environmental and economic impact. Moreover, studies from the National University of Colombia have shown that a dam failure is likely unless an emergency plan is adopted. The safety of the downstream communities has been highlighted as being critical.[22][23] By November 2022, drills had evacuated 5,000 people to prepare for the operation of the dam.[24]

See also

  • List of power stations in Colombia

References

  1. ^ "Primera turbina de Hidroituango empieza a operar el 30 de noviembre: Irene Vélez" [The first turbine at Hidroituango will begin operating on November 30: Irene Vélez] (in Spanish). 18 October 2022.
  2. ^ "Chadbourne Represented EPM Ituango in BOOMT Contract for the 2400 MW Hidroituango Project". 28 April 2011. Retrieved 9 July 2011.{{cite web}}: CS1 maint: deprecated archival service (link)
  3. ^ "China, South Korea companies in race for Colombia hydropower deal". Colombia Reports. 3 February 2010. Archived from the original on 21 September 2010. Retrieved 9 July 2011.
  4. ^ "Evolution of Expansion Plans" (PDF). EPM. Retrieved 9 July 2011.
  5. ^ "Colombia hydro utility to build 2,688-MW Pescadero Ituango". HydroWorld. 7 December 2011. Archived from the original on 13 March 2012. Retrieved 9 July 2011.
  6. ^ "Construction preparation begins for 2,400-MW Ituango in Colombia". Hydro World. 22 September 2011. Archived from the original on 24 March 2016. Retrieved 29 March 2012.
  7. ^ "Consortium wins US66 million contract for Ituango hydro project build in Colombia". HydroWorld. 8 July 2011. Archived from the original on 13 March 2012. Retrieved 9 July 2011.
  8. ^ "Datos Técnicos" (in Spanish). Hidroeléctrica Ituango. Retrieved 9 July 2011.
  9. ^ a b "Reabren 3 túneles para evacuar aguas embalsadas en Hidroituango" [Three tunnels reopen to drain water impounded at Hidroituango] (in Spanish). Caracol Radio. 8 May 2018. Retrieved 17 May 2018.
  10. ^ "Nuevo derrumbe en proyecto Hidroituango" [New landslide at the Hidroituango project] (in Spanish). El Colombiano. 30 April 2018. Retrieved 17 May 2018.
  11. ^ "Se agrava situación en Hidroituango, deberán inundar casa de máquinas" [The situation at Hidroituango worsens; they will have to flood the powerhouse.] (in Spanish). El Tiempo. 10 May 2018. Retrieved 17 May 2018.
  12. ^ "Así fue el destaponamiento del túnel de Hidroituango" [This is how the Hidroituango tunnel was unblocked] (in Spanish). El Colombiano. 12 May 2018. Retrieved 17 May 2018.
  13. ^ "Hidroituango: cuatro puentes afectados deja incremento del nivel de aguas del río Cauca" [Hidroituango: Four bridges affected by the rising water level of the Cauca River] (in Spanish). W Radio. 13 May 2018. Retrieved 17 May 2018.
  14. ^ ""Hubo una obstrucción en la casa de máquinas": EPM sobre emergencia en Hidroituango" ["There was an obstruction in the powerhouse": EPM on the emergency at Hidroituango] (in Spanish). El Espectador. 16 May 2018. Retrieved 17 May 2018.
  15. ^ "'Existe la posibilidad de que se rompa la presa de Hidroituango': gerente de EPM" ['There is a possibility that the Hidroituango dam could break': EPM manager] (in Spanish). El Espectador. 17 May 2018. Retrieved 17 May 2018.
  16. ^ "Colombia Ituango Dam Emergency 22 May 2018" (PDF). Relief Web. European Commission. Retrieved 25 May 2018.
  17. ^ "Hidroituango dam fail emergency". Science Engineering & Sustainability. 24 March 2019. Retrieved 24 March 2019.
  18. ^ "Hidroituango hydropower dam Colombia. Opinion from Dr Ordoñez". Science Engineering & Sustainability. 24 March 2019. Retrieved 24 March 2019.
  19. ^ Naomi Cohen (16 January 2017). "Colombia's other war". Le Monde diplomatique. Retrieved 28 January 2017.
  20. ^ Edgar Domínguez (13 March 2013). "Hidroituango avanza con beneficios para Antioquia" [Hidroituango is moving forward with benefits for Antioquia]. Portfolio (in Spanish). Retrieved 6 February 2019.
  21. ^ Hidroituango: investigan al alcalde de Medellín y al gobernador de Antioquia [Hidroituango: The mayor of Medellín and the governor of Antioquia are under investigation] (in Spanish), 11 February 2019, retrieved 12 February 2019
  22. ^ "Estudio de la Universidad Nacional revela panorama preocupante del futuro de Hidroituango" [Study by the National University reveals a worrying outlook for the future of Hidroituango]. Noticias Caracol (in Spanish). 6 February 2019. Retrieved 12 February 2019.
  23. ^ Hidroituango es una amenaza para comunidades en área de influencia: científico Portilla [Hidroituango is a threat to communities in the area of influence: scientist Portilla] (in Spanish), archived from the original on 13 February 2019, retrieved 12 February 2019
  24. ^ "EPM evacuates downstream towns in test before starting 2.4 GW Ituango hydro". Hydro Review. 16 November 2022.